At Modified Concrete Suppliers, LLC, we have been involved with numerous types of schedules on Fast Track Projects. Below, are three examples:

Fast Track Projects

6 Day Projects
• 1 Hydro Machine
• Type III Latex Modified Concrete – 2 day cure – 1 wet, 1 dry
• Rotomill ½ day, Hydro 2 ½ days, Pour 1 day, Cure 2 days

Weekend Projects
• 2 Hydro Machines
• Rapid Set Latex Modified Concrete – 3 hours wet cure = 2,500 psi
• Rotomill 6 hours, Hydro 12 hours, Pour 4 hours, Cure 24 hours
• Can be performed in phases

Overnight Projects
- 2 Hydro Machines
- Rapid Set Latex Modified Concrete – 3 hours wet cure = 2,500 psi
- Rotomill 2 hours, Hydro 5 - 6 hours, Pour 2 hours, Cure 2 - 3 hours
- Can be performed in phases

Call us today for scheduling information on Fast Track Projects.